Sample Plan — Product Development Plan

vision
Develop economically viable solution to 6782 printer memory error problem by 12/1/09

mission
Reduce the incidence of printer fatal error messages

objectives
blue dot Achieve .0000032 per thousand memory errors per average test cycle by 9/1/09
blue dot Keep cost of upgrade to $1.53 per shipped unit
blue dot Operate within budget of $356,000.00

strategies
blue dot Use 3 teams of 2 engineers plus 2 outside consultants
blue dot Concentrate on fixing current design rather that replacing it with another
blue dot Hold weekly progress meeting with team to review progress against plan/budget
blue dot Use outside consultants on as needed basis for new laser technologies

plans
blue dot Establish teams by 3/1
blue dot Identify and qualify 2 outside consultants; finalize contracts by 3/1
blue dot Complete problem assessment by 5/31
blue dot Propose an engineering solution by 6/30
blue dot Complete prototypes by 7/31
blue dot Complete product trials by 8/30
blue dot Document final product specs by 9/30
blue dot Complete installation of modified production equipment by 11/30

  This plan is a static sample. To see performance scorecards
and progress reports go to the