Develop economically viable solution to 6782 printer memory error problem by 12/1/07
Reduce the incidence of printer fatal error messages
Achieve .0000032 per thousand memory errors per average test cycle by 9/1/07
Keep cost of upgrade to $1.53 per shipped unit
Operate within budget of $356,000.00
Use 3 teams of 2 engineers plus 2 outside consultants
Concentrate on fixing current design rather that replacing it with another
Hold weekly progress meeting with team to review progress against plan/budget
Use outside consultants on as needed basis for new laser technologies
Establish teams by 3/1
Identify and qualify 2 outside consultants; finalize contracts by 3/1
Complete problem assessment by 5/31
Propose an engineering solution by 6/30
Complete prototypes by 7/31
Complete product trials by 8/30
Document final product specs by 9/30
Complete installation of modified production equipment by 11/30